Information Collection Request

FERC-725U, (RD22-3) Mandatory Reliability Standards: Reliability Standard CIP-014

ICR 202209-1902-004 · OMB 1902-0274 · Received in OIRA

Forms and Documents
DocumentTypeStatusAvailability
FERC 725U supporting statement-9-15-2022-Final (2)9-20-22.docx Supporting Statement A Uploaded 2022-09-20 Repair queued
20220616-3032_RD22-3-000.docx Supplementary Document Uploaded 2022-09-20 Repair queued
RD22-3 FERC 725U 30-day notice (published).pdf Supplementary Document Uploaded 2022-09-15 Missing upstream
RD22-3-000 60-day notice (published).pdf Supplementary Document Uploaded 2022-09-15 Missing upstream
RD22-3 30-day notice 9-1-22 (Issued).docx Supplementary Document Uploaded 2022-09-15 Repair queued
RD22-3-000 (Issued).docx Supplementary Document Uploaded 2022-09-15 Available
CIP-014-3.pdf Supplementary Document Uploaded 2022-09-15 Missing upstream
16 USC 824 (o).pdf Supplementary Document Uploaded 2021-02-12 Repair queued
18 CFR 40.pdf Supplementary Document Uploaded 2021-02-12 Repair queued
IC Document Collections
IC IDCollectionTypeStatusForm
212410 Reliability Standard CIP-014-3 Modified
ICR Details
1902-0274 202209-1902-004
Received in OIRA 202102-1902-001
FERC FERC-725U
FERC-725U, (RD22-3) Mandatory Reliability Standards: Reliability Standard CIP-014
Revision of a currently approved collection   No
Regular 09/20/2022
  Requested Previously Approved
36 Months From Approved 05/31/2024
344 336
11,254 10,991
0 0

RD22-3 will approve the removal of the evidence retention provision in section C.1.1.4 of the compliance section of Reliability Standard CIP-014-2, will allow NERC to monitor compliance more effectively without compromising the confidentiality of sensitive information. Accordingly, we approve NERC’s petition and accept the proposed Reliability Standard CIP-014-3, to become effective on the date of issuance of this order. The Reliability Standard CIP-014-3 requires Transmission Owners and Transmission Operators to identify and protect Transmission stations and Transmission substations, and their associated primary control centers, that if rendered inoperable or damaged as a result of a physical attack could result in widespread instability, uncontrolled separation, or cascading within an Interconnection. In terms of information collection requirements, there are two main types of PRA activities: 1) Create or maintain documentation showing performance of a certain task; and 2) Develop a physical security plan.

US Code: 16 USC 824o Name of Law: Federal Power Act
  
None

Not associated with rulemaking

  87 FR 37847 06/24/2022
87 FR 54991 09/08/2022
No

1
IC Title Form No. Form Name
Reliability Standard CIP-014-3

  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 344 336 0 8 0 0
Annual Time Burden (Hours) 11,254 10,991 0 263 0 0
Annual Cost Burden (Dollars) 0 0 0 0 0 0
Yes
Miscellaneous Actions
No
Each requirement (including record-keeping requirements) in CIP-014-3 have been updated to reflect the normal fluctuations in hours and responses. A increase of 8 in responses and increase of 263 in burden hours. There were no net changes to burden due to Docket RD22-3 Modifications.

$8,279
No
    No
    No
No
No
No
No
David O'Conner 202 502-6695

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
09/20/2022