Information Collection Request

FERC-917/918: Electric Transmission Facilities (extension)

ICR 202409-1902-005 · OMB 1902-0233 · Received in OIRA

Forms and Documents
DocumentTypeStatusAvailability
18 CFR 35.28.docx Supplementary Document Uploaded 2024-09-19 Repair queued
20240809-3021_Final_FERC-917 and 918 30 Day Notice.docx Supplementary Document Uploaded 2024-09-17 Repair queued
20240603-3044_Final_FERC-917 and 918 60-day Notice_6_3_2024.docx Supplementary Document Uploaded 2024-09-17 Repair queued
FERC 917_918 Fed Reg. June 7_24.pdf Supplementary Document Uploaded 2024-09-17 Repair queued
FERC 917_918 Fed Reg. Aug 15 24.pdf Supplementary Document Uploaded 2024-09-17 Missing upstream
Final_FERC-917_918_Supporting Statement_2024.docx Supporting Statement A Uploaded 2024-09-17 Missing upstream
Pro Forma OATT-Att.pdf Supplementary Document Uploaded 2024-06-12 Missing upstream
16 U.S.C. 824e.pdf Supplementary Document Uploaded 2022-05-06 Repair queued
IC Document Collections
IC IDCollectionTypeStatusForm
268435 RM21-17: Sharing Information between planning regions Unchanged
268434 RM21-17: Evaluating Alternative Transmission Technologies (without OATT) Unchanged
268433 RM21-17: Evaluating Alternative Transmission Technologies (with OATT) Unchanged
268432 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (with OATT) (One-time) Unchanged
268431 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (without OATT) (One-Time)) Unchanged
268430 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (without OATT) (Ongoing) Unchanged
253277 RM21-17: Consider in the regional transmission planning processes regional transmission facilities that address certain interconnection-related needs Unchanged
253275 RM21-17: Seek agreement from the states to establish a Long-Term Regional Transmission Cost Allocation Method and/or a State Agreement Process (Year 1) Unchanged
253274 RM21-17: Revise the regional transmission planning process - Right-sizing transmission (with OATT) (Ongoing)) Unchanged
253272 RM21-17: Revise OATT to comply with regional transmission planning process (One-Time)) Unchanged
253271 RM21-17: Participate in Long-Term Regional Transmission Planning (With OATT)) Unchanged
253270 RM21-17: Participate in Long-Term Regional Transmission Planning (Without OATT)) Unchanged
179057 FERC-918, Information to be Posted on the OASIS and Auditing Transmission Service Information (Standards) Modified
179056 FERC-917, Non-discriminatory Open Access Transmission Tariff Modified
ICR Details
1902-0233 202409-1902-005
Received in OIRA 202403-1902-009
FERC FERC-917/918
FERC-917/918: Electric Transmission Facilities (extension)
Extension without change of a currently approved collection   No
Regular 09/19/2024
  Requested Previously Approved
36 Months From Approved 11/30/2024
1,016 1,016
470,354 460,969
0 0

The Federal Energy Regulatory Commission (FERC or Commission) requests that the Office of Management and Budget (OMB) review the extension of the FERC-917 & 918 information collection. The information collection activities up for renewal were that were the existing requirements prior to FERC Order 1920 in Docket No. RM21-17-000. At the time of the drafting of the final rule in the FERC"s Order 1920, the collection was up for renewal. The extension was not included in the final rule because FERC did not request the extension at the time of the Notice of Proposed Rulemaking (NOPR). Therefore, the Commission issued two public notices requesting comment on the existing requirements unrelated to the FERC Order 1920. The Commission did not receive any comments.

US Code: 16 USC 824e Name of Law: Federal Power Act
  
None

Not associated with rulemaking

  89 FR 48609 06/07/2024
89 FR 66381 08/15/2024
No

  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 1,016 1,016 0 0 0 0
Annual Time Burden (Hours) 470,354 460,969 0 0 9,385 0
Annual Cost Burden (Dollars) 0 0 0 0 0 0
No
No
There is a small increase in burden hours in this request for extension due to an agency adjustment in our estimate. Previously, the burden hours related to maintaining and submitting the Non-Discriminatory Open Access Transmission Tariff reflected 508 hours per response, but now believes a better estimate is 566 hours per response. This adjustment results in an increase in burden hours of 9,385.

$1,462,898
No
    No
    No
No
No
No
No
Christopher Kozler 734 239-3294 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
09/19/2024