Information Collection Request

FEMA Preparedness Grants: Port Security Grant Program (PSGP)

ICR 202309-1660-007 · OMB 1660-0114 · Received in OIRA

Forms and Documents
DocumentTypeStatusAvailability
Form FEMA Form FF-207-F Grant Programs Directorate Extension Request (GPD-Extension) (Private Sector)) Form New Repair queued
Form FEMA Form FF-207-F Grant Programs Directorate Extension Request (GPD-Extension) (SLTT) Form New Missing upstream
Form FEMA Form FF-207-F Grant Programs Directorate Performance Report (GPD-PR) (Private Sector) Form and Instruction New Repair queued
Form FEMA Form FF-207-F PSGP Investment Justification (Private Sector) Form New Repair queued
Form FEMA Form FF-207-F Grant Programs Directorate Performance Report (GPD-PR) (SLTT) Form and Instruction Modified Repair queued
Form FEMA Form FF-207-F PSGP Investment Justification (SLTT) Form Modified Missing upstream
MOU.docx Supplementary Document Uploaded 2023-11-13 Available
Narrative of Changes Table IJ Template 2019.docx Supplementary Document Uploaded 2020-05-19 Repair queued
1660-0114 - 30-Day Revision FRN - 2023 11 17.pdf Supplementary Document Uploaded 2023-11-21 Repair queued
1660-0114 - 60-Day Revision FRN - 2023 09 06.pdf Supplementary Document Uploaded 2023-09-08 Repair queued
1660-0114 - Supporting-Statement A - 2023 11 21 clean.docx Supporting Statement A Uploaded 2023-11-21 Repair queued
Public Law 107-295, Maritime Transportation Security Act of 2002.pdf Supplementary Document Uploaded 2017-01-19 Repair queued
privacy_PIA_FEMA_GrantManagementPrograms_February2015.pdf Supplementary Document Uploaded 2017-01-25 Repair queued
FY_2016_PSGP_NOFO_FINAL.pdf Supplementary Document Uploaded 2017-01-19 Repair queued
Public Law 109-347 (46 USC 70107), Section 112.pdf Supplementary Document Uploaded 2010-04-07 Repair queued
ICR Details
1660-0114 202309-1660-007
Received in OIRA 202005-1660-003
DHS/FEMA
FEMA Preparedness Grants: Port Security Grant Program (PSGP)
Revision of a currently approved collection   No
Regular 11/30/2023
  Requested Previously Approved
36 Months From Approved 12/31/2023
1,832 1,759
17,446 17,450
0 0

Section 102 of the Maritime Transportation Security Act of 2002, as amended (46 U.S.C. § 70107), authorizes the PSGP to provide for the risk-based allocation of funds to implement Area Maritime Transportation Security Plans and facility security plans among port authorities, facility operators, and State and local government agencies required to provide port security services and to train law enforcement personnel under 46 U.S.C. § 70132. Before awarding a grant under the program, the Secretary for Homeland Security shall provide for review and comment by the appropriate Federal Maritime Security Coordinators and the Maritime Administrator. In administering the grant program, the Secretary shall take into account national economic, energy, and strategic defense concerns based upon the most current risk assessments available.

PL: Pub.L. 109 - 347 Section 112 Name of Law: SECURITY AND ACCOUNTABILITY FOR EVERY PORT ACT OF 2006
  
None

Not associated with rulemaking

  88 FR 60964 09/06/2023
88 FR 80325 11/17/2023
No

  Total Request Previously Approved Change Due to New Statute Change Due to Agency Discretion Change Due to Adjustment in Estimate Change Due to Potential Violation of the PRA
Annual Number of Responses 1,832 1,759 0 -27 100 0
Annual Time Burden (Hours) 17,446 17,450 0 -54 50 0
Annual Cost Burden (Dollars) 0 0 0 0 0 0
No
Yes
Cutting Redundancy
FEMA estimates a decrease of 54 burden hours from the discontinuation of the PSGP – MOU or MOA template, which is offset by an increase of 50 burden hours from the introduction of FEMA Form FF-207-FY-23-110, GPD-Extension. This gives an overall decrease of 4 burden hours. FEMA estimates a decrease in annual cost burden of $4,426 from the discontinuation of the PSGP MOU or MOA template; an increase of $4,191 from the introduction of FEMA Form FF-207-FY-23-110, GPD-Extension, and an increase of $32,149 from an increase of wages for FEMA Forms FF-207-FY-23-110, PSGP IJ and FF-207-FY-23-110, GPD-PR ($31,601 + $548 = $32,149). This gives an overall increase in cost burden of $27,723.

$1,853,355
No
    No
    No
No
No
No
No
Kevin Crosby 202 550-6482 [email protected]

  No

On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
 
 
 
 
 
 
 
    (i) Why the information is being collected;
    (ii) Use of information;
    (iii) Burden estimate;
    (iv) Nature of response (voluntary, required for a benefit, or mandatory);
    (v) Nature and extent of confidentiality; and
    (vi) Need to display currently valid OMB control number;
 
 
 
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.
11/30/2023