The affected entities are subject to the General Provisions of the NESHAP at 40 CFR part 63, subpart A, and any changes, or additions to the Provisions specified at 40 CFR part 63, subpart RRRR.
Owners or operators of the affected facilities must submit a one-time-only of any physical or operational changes, initial performance tests, and periodic reports and results. Owners or operators are also required to maintain records of the occurrence and duration of any startup, shutdown, or malfunction in the operation of an affected facility, or any period during which the monitoring system is inoperative. Reports are also required semiannually.
There is a small decrease in the respondent labor hours and an increase in the O&M cost from the previous ICR due to rounding. In this ICR, we have rounded total values to three significant digits.
There is a decrease in the total estimated labor costs due to a correction. The previous ICR incorrectly referenced managerial labor rates when calculating technical labor cost, and vice versa, thereby overestimating total labor costs.
On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control number;
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.