In accordance with 5 CFR 1320, the information collection is approved for three years.
Inventory as of this Action
Requested
Previously Approved
04/30/2016
36 Months From Approved
04/30/2013
236
0
345
165,900
0
120,377
8,691
0
9,076
10 CFR Part 55, ÂOperators Licenses, of the NRCÂs regulations, specifies information and data to be provided by applicants and facility licenses so that the NRC may make determinations concerning the licensing and requalification of operators for nuclear reactors, as necessary to promote public health and safety. The reporting and recordkeeping requirements contained in 10 CFR Part 55 are mandatory for the licensees and applicants affected.
The industry burden increased by 45,523 hours from 120,377 to 165,900 hours, and the industry costs increased by $16,806,874 from $28,649,726 to $45,456,600. These changes are based on NRC and facility staff experiences and are specifically addressed below. The hourly rate has increased from $238/hr. to $274/hr.
Reporting Burden Increases:
55.11 Â Burden per response increased by 15 hours from 40 to 55 hours based on averaged actual sites' experiences reported to the NRC.
55.40 (b) (1) and (3) ÂBurden per response increased by 500 hours from 2,000 to 2,500
hours based on averaged actual sites' experiences reported to the NRC.
55.59(c) Â The number of power site respondents increased by 54 from 16 to 70 and the number of non-power site respondents increased by 31 from 0 to 31 to show the exact number of reporting sites and the number of hours increased by 16 from 0 to 16 for non-power sites. During the previous extension the number of power and non-power sites were inadvertently misstated and are being corrected with this extension.
Additional Industry costs increased because the cost of reproducing final examinations for each applicant increased by .05 from .05 to .10 per page. Storage and equipment costs increased because the number of recordkeeping hours increased by 5,305 hours from 28,369 to 33,674.
Reporting Burden Decreases:
The previously reported number of respondents was inadvertently calculated and is being corrected in this extension. The number of respondents has decreased by 142 from 243 to 101 (70 Power Sites + 31 Non-power Sites).
55.40(a) Â Power site response burden decreased by 45 hours from 100 to 55 hours based on the actual increase in the use of electronic transfer of examination information and materials.
Recordkeeping Burden - Increases:
55.59(a)(2) Â The burden increased for power sites by 58 hours from 100 to 158 hours, and for non-power sites the burden increased by 5 hours from 0 to 5 hours based on averaged actual sites' experiences reported to the NRC.
Industry Recordkeeping Burden - Decreases:
The number of recordkeepers decreased by 1 from 102 to 101 (70 power sites + 31 non-power sites) because 1 Non-power Site (University of Arizona) was decommissioned.
55.40(b)(2) Â The burden hours per power site recordkeeper decreased by 84 hours from 100 to 16 hours because all affected licensees have completed the requirements and now perform maintenance.
On behalf of this Federal agency, I certify that the collection of information encompassed by this request complies with 5 CFR 1320.9 and the related provisions of 5 CFR 1320.8(b)(3).
The following is a summary of the topics, regarding the proposed collection of information, that the certification covers:
(i) Why the information is being collected;
(ii) Use of information;
(iii) Burden estimate;
(iv) Nature of response (voluntary, required for a benefit, or mandatory);
(v) Nature and extent of confidentiality; and
(vi) Need to display currently valid OMB control number;
If you are unable to certify compliance with any of these provisions, identify the item by leaving the box unchecked and explain the reason in the Supporting Statement.